April
28 - Sunday
Moved
decorative plants and pads for plant pots.
April
29 - Monday
Mike
Fountain layed out and dug the 10x20 foot foundation for the addition to the garage. Issues :
design approved v. thot, electric and water lines for watering system,
landscape edging out, and tree transplant. Lite rain at 1:00. Delivers digger
and carrier. Moved arbor vitae tree. Who knows... Mike Fountain did not return
after his physician's appointment yesterday.
April
30 - Tuesday
Lite
rain over nite... Should dig today anyway.... Dug footer 4' wide and 5' deep,
must be below 3'6" for the freeze line.
If not rain, footer tomorrow... 83 high.
May
7 - Tuesday
Got green card from the building
inspector saying we can form and pour when ready.
May
8 - Wednesday
Came
mid afternoon and formed the footer.. Then at 4:30 it was poured in spite of
red card from the Inspector who came at 1:00
May
9 - Thursday
Remove
forms for footers and install wall forms. Rain started at 9:00. Formed and
poured by 2:30 in mild sprinkle. Re-inspected and approved.
May
10 - Friday
Forms
off the walls.. Tuesday to back fill.. Told Ben (sprinkler man) so he could
reconnect the watering system . Tip $60
May
14 - Tuesday
Dirt
hauled, backfill, gravel into interior of addition foundation by Mike.
May
15 - Wednesday
Poured
the floor about 3:00 and finished at 8:00. Tip $20
May
16 - Thursday
Sprayed
sealant on concrete
May
17 - Friday
Rain..
Mike worked out roofline with architectural committee.
May
20 - Monday
Framing
was to begin. Trash wagon came.. No
carpenters showedMay 21-Tuesday
Wood is delivered and visit from Kris.
May 23 - Thursday
Up at 2 am... Pissed and frustrated over addition. Emailed Mike and got a 8:30 meeting with him
and Kris. Did not look as bad as we thought and they guaranteed finishing so
not so high and eyesore. More comfortable. Staying away from
construction. Wall and rafters in and
covered. Tyvek covered. Tomorrow odds
and ends and roofer.
May 24 - Friday
Two workers finish overhang on south... And some other odds
and ends. Finished closing in and adding hanger boards. Then late the guy came
to seal the roof and put on the metal sides... Roof shingles tomorrow.
May 25 - Saturday
Working on shingles most of the day...
May 26 - Sunday
Worked on roofing and flashing... Out of material so cannot
finish until Tuesday
May 28 - Tuesday
Steve the electrician coming for wiring and plugs. Plumber,
Nick, coming for toilet and outside spigot in back of house. Eric here to order
inspection of framing and electrical.
May 30 - Thursday
Inspection completed and ready to insulate and electrify.June 1 - Saturday
Eric and the insulation person to insulate today... Eric 3/helper 2
June 7- 14
Interior drywall installed and finished
June 20 week
Finish dry wall... Painting ... Down spout for emergency
drainage on deadend gutterJuly 6
Kris worked all day and at least until 8:10 on facia and soffit.
July 9 - Tuesday
Fritz (landscaper) called this AM. We are doing a walk-around Thursday afternoon to discuss the schedule and plan. Special ordered siding shingles to arrive at Brunsell today and Kris is to start installing Thursday after painting them tomorrow.
July 10 - Wednesday
No call from Kris confirming
tomorrow's installation.July 11 - Thursday
Message from Kris that our shingles did not arrive on Tuesday and should come in tomorrow. If so, Kris will paint them over the weekend and possibly install Monday and/or Tuesday.
Good afternoon meeting with Fritz, the landscaper to begin
developing a plan
July 14, 15, 16 - Sunday, Monday, Tuesday
Siding by Kris after an overwhelming 2 days of cutting, sanding and some painting of the
shingles.
July 14 - Sunday
Ben is scheduled to come tomorrow eve to start the
sprinkler system and set it to run 1 X per wk.July 15 - Monday
Kris and assistant Dan worked all day installing and painting shingles and horizontal board.
July 16 - Tuesday
Kris and Dan finished touch-up and garden wagon bed,
uncovered light bulb, installed interior window frames. Done at 11:30. Dan $20
tip, Kris $80 for extra work beyond
contract. Kris gave us all the paint cans and cleaned up pretty well. I
organized the leftover boards, primed both sides of the wagon bed and prepared
the garage floor for scrubbing to remove construction mud and drywall mud.
July 18 - Thursday
The garage floor is done except for one last spray down and
vacuum. Got mud and most drywall mud up. I will finish the garage tomorrow morning
then move all the cars in late day after it dries.
July 19 - Friday
Steve here to hang fluorescent light in addition, install
all sockets and covers including outside. Dismantled inoperative light fixture
in our bathroom - socket is shot. He recommends taking to Madison Lighting for
repair. No extra charge for his work
today.
July 22 - Monday
Meet with Mike re landscaping. Results: Fritz will do all
the work, including the yard repair. We pay Mike $400 total and he'll pay Fritz
for labor and materials. No paver wall will be used, as originally thought.
July 23 - Tuesday
Rick home from trip westJuly 25, 26 - Thursday, Friday
Landscaping by Fritz
August 19
Grass is up, having been watered
daily since July 26 (3 1/2 wks). Some areas were overseeded to cover spots
where birds ate the grass seed that wasn't adequately covered by straw.
The shop to the right ... The garage below with the
addition in the right pix where the ABC sports flag, which Marnie "procured" while in college,
hanging on the wall and the motorcycles are parked.
No comments:
Post a Comment